How long does it take to install a heat pump in an oil-heated Devon home? About a week on site. The team starts on a Monday and James commissions the system on the Thursday or Friday, with the survey, the design and the grant application all done in the weeks before.
Key Takeaways
- An oil or LPG swap takes 4 or 5 working days on site, Monday to Thursday or Friday, once the survey, design and grant application are done.
- If you qualify, the grant comes off your quotation and invoice, and the scheme gives the installer 120 days from applying to commission.
- The two-man electrical team Eco Pro works with finishes most installs’ electrics in a day, alongside a two-man install team doing the fitting.
- Across East Devon, Teignbridge and Mid Devon, James takes on one or two installs at a time, designs each one and commissions it himself.
- The free home assessment is where your own dates start, so you can plan the week around them.
Once you know a heat pump suits the house, the next question is how much of your week it takes over. For an oil home the answer depends less on the heat pump than on the house around it: how many radiators change, where the cylinder goes and how far the pipes run.
How Long Does a Heat Pump Installation Take? About a Week on Site
Illustration: the outdoor unit in the garden, pipework through the wall to the hot water cylinder, a radiator and the controls.
That week assumes the design is finished and nothing unusual sits in it. A longer list of radiator changes, underfloor heating or a cylinder in a new spot adds days, and the survey shows which of those apply to you.
The week stays short because the thinking happens first. By the Monday James has measured the heat loss, chosen the heat pump and cylinder, drawn up every radiator change and sent the grant application, so the team spends its days fitting. The page for our air source heat pump installation service covers what the job includes.
The install week
Before
The weeks ahead
Free home assessment, heat loss survey, design, grant application
Monday
Start
Install team on site; the old system starts coming out
Midweek
Fitting
Cylinder, pipework and any radiator changes from the design
One day
In the week
Electrics, most installs done in a day
Thursday or Friday
Handover
Commissioning, controls set up, handover
The usual shape of an oil or LPG swap. Your dates are booked after the survey.
Before the Week: Home Assessment, Heat Loss Survey and Design
The heat pump installation process starts weeks before anyone lifts a floorboard. At the free home assessment James checks whether the house suits a heat pump, looks at where the outdoor unit and cylinder could go, and leaves you a fixed estimate. Book the next step and the heat loss survey (free if you go ahead with the install; £250 plus VAT if you decide not to) measures every room; our guide to what the heat loss survey measures explains the method.
The survey settles what is needed to install a heat pump in your house: its size, the cylinder, a radiator schedule and the controls. Eco Pro then applies for the Boiler Upgrade Scheme grant on your behalf, and the scheme gives the installer 120 days from that application to install and commission the system, so your dates follow the paperwork.
The four steps before Monday
Free home assessment
Suitability, positions and a fixed estimate on the spot.
Heat loss survey and design
Every room measured; heat pump, cylinder and radiators chosen.
Dates booked
The week goes in the diary around the team and your plans.
Monday: The Air Source Heat Pump Installation Starts on Site
The install team arrives on the Monday and drains the old system. Early in the week the team disconnects the oil boiler and takes it out, and sets the outdoor unit on its base where the survey put it, the same first stage of any oil boiler replacement in Devon that Eco Pro takes on.
Your plan covers the oil tank as well as the boiler, so you and James settle it before the week starts. For what else changes in the house when oil goes, from deliveries to the space by the back door, read the full oil to heat pump guide.
Early in the week
Going out
The oil boiler and its old controls, once the team drains the system.
Coming in
The outdoor unit on its base, and the pipe route through the wall to the cylinder.
Midweek: Cylinder, Pipework and Radiator Changes
Midweek the work moves indoors, to the spot where the oil boiler stood and the cupboard or utility room chosen for the cylinder. The team fits the cylinder in the spot agreed at the survey, runs and lags the pipework between it, the outdoor unit and the radiators, and swaps any radiator the design flagged as too small for a heat pump’s cooler water. Our guide on how the cylinder is chosen explains why its size and position matter.
Rooms the team will need to reach
- The cupboard, utility room or garage where the cylinder goes
- Every room on your radiator schedule
- The loft or the space under the floor where pipes run
- The outside wall where the pipes go through to the unit
The Electrics: About a Day for the Electrical Team
The two-man electrical team Eco Pro works with wires in the heat pump and its controls, and on most installs they finish their part in a day. Some houses need more, such as an older consumer unit. Ask James at the free home assessment whether your consumer unit needs work.
The electrics
1 day
The electrics on most installs
Done by the two-man electrical team Eco Pro works with. An older consumer unit can add to that day.
Thursday or Friday: Commissioning and Handover
At commissioning James fills and balances the system, sets the controls and the hot water temperature from the design, and checks it runs to the figures on the paperwork. He registers the manufacturer’s warranty at commissioning for every make: Ideal heat pumps carry seven years’ parts and labour as standard, and other makes carry their maker’s own term.
At handover he walks you through the controller, the settings that matter and the ones to leave alone, and the IWA workmanship warranty and deposit insurance cover the job. If you qualify, the grant comes off what you pay, shown on your quotation and invoice, and Ofgem may phone or visit to check the installation.
Living at Home During the Install Week
Illustration: a dining room with a long double-panel radiator under the window.
Households usually stay at home through the install. The disruption of a heat pump installation looks like a team in and out of the house each day, doors open while pipes go through the wall, and some noise where boards come up for a pipe run. If you have a dog that takes against strangers, mention it at the survey; the back door will be busy.
Ask James at the free home assessment how the week would run in your house, and who at home needs to stay warm through it.
Before Monday
- Clear the cylinder cupboard or utility corner
- Leave a route from the drive to where the unit goes
- Room for the team’s vans
- Tell James at the first visit who is at home during the day
What Can Stretch the Heat Pump Installation Time
Illustration: a radiator valve on a copper pipe rising through the floor beside a panel radiator.
Some jobs run past the week. The usual reasons show up at the survey:
- Small-bore pipes that need new, larger runs for a heat pump’s flow, on top of radiator changes
- Underfloor heating in a room or two
- A cylinder moving to the garage or an outbuilding, with longer pipe runs to it
- Electrical work beyond wiring in the new system
Frequently Asked Questions
Illustration: a bedroom with a panel radiator under the window.
About a week on site for an oil or LPG home; the timeline at the top of this guide shows the order. The survey, design and grant application come before it.
Get your own week planned at a free home assessment.
Space outside for the unit, room for a cylinder, radiators that can heat each room on a heat pump’s cooler water, and an electrical supply that can take it. The heat loss survey checks each one for your house.
Ask James what your house would need at a free home assessment.
Usually not. Households tend to stay put through the week, with the team in and out each day and some rooms in use for pipework and radiators.
Talk through your household’s week at a free home assessment.
The survey and design come first, then the grant application, and the scheme gives the installer 120 days from applying to install and commission. James books your week once the design and application are done.
Start the clock with a free home assessment.
More radiator changes, underfloor heating, a cylinder moving to a new position, or extra electrical work. These usually show up at the survey.
Find out what applies to your house at a free home assessment.
Sometimes. An older consumer unit may need changing, so mention its age when you book the free home assessment.
Talk through your electrics at a free home assessment.
Before you pay, if you qualify. Eco Pro applies on your behalf and takes the grant off the amount you pay for installation, shown on your quotation and invoice.
Check if you qualify at a free home assessment.
Plan Your Install Week Around Your Diary
Come to the free visit with the dates you would like in mind. James gives you a straight answer on suitability and a fixed estimate, then tells you how the survey, the design and the grant application line up behind those dates.
Book my free home assessmentPrefer to talk it through first? Ring 01395 202030. James answers, and he is the person who will price the job.
★★★★★
“The installation was carried out professionally with great attention to detail and a high standard of workmanship.”
Barbara Murphy · Google review